JOHOR BAHRU - About two-thirds of civil infrastructure works on the Singapore side of the Johor Bahru-Singapore Rapid Transit System (RTS) Link have been completed, with passenger service slated to start by December 2026.
On the Malaysian side, the project has reached 65 per cent completion as at Dec 31, 2023.
In a joint statement, the transport ministries of both countries said a significant construction milestone was reached at the end of December 2023, with the completion of a 17.1m-long concrete span connecting the Singapore and Malaysian ends of a rail viaduct that will run across the Strait of Johor.
On Jan 11, Prime Minister Lee Hsien Loong and Malaysian Prime Minister Anwar Ibrahim met at the strait in a ceremony to commemorate the milestone.
The two leaders signed plaques symbolising the shared commitment of both countries to deliver the cross-border rail link, which was delayed and suspended for six months at one point, before new terms were agreed and the project resumed.
PM Lee later wrote on Facebook that the span “bridges our two piers, and brings our friendship and bilateral ties closer”.
He noted that he and Datuk Seri Anwar had emphasised win-win cooperation when they last met in Singapore at the Singapore-Malaysia Leaders’ Retreat in October 2023.
Catch up on the news that everyone’s talking about
Thank you!
Sign up
By signing up, you agree to our Privacy Policy and T&Cs.
“I am glad that we are making progress,” said PM Lee.
“As we approach the 60th anniversary of bilateral relations next year, I look forward to both countries charting new areas of cooperation, including in trade and investment, tourism, innovation, and the digital and green economies.”
The transport ministries said passenger service for the RTS Link is targeted to start by December 2026.
When ready, the 4km rail shuttle service will be able to carry up to 10,000 people per hour in each direction between Bukit Chagar in Johor and Woodlands North, absorbing at least 35 per cent of the human traffic at the Causeway and easing congestion on the land link.
According to Malaysia’s Mass Rapid Transit Corporation (MRT Corp), the service will operate from 6am to midnight, with trains running at four-minute intervals during peak hours.
With the connecting span now done, construction work for the rest of the RTS Link’s civil infrastructure – which includes the rail viaduct, tunnels, stations and Customs buildings – will continue on both sides, the transport ministries said.
Remote video URL
In a press conference after the ceremony, Malaysian Transport Minister Anthony Loke said the RTS infrastructure is on schedule to be completed by December 2024.
“We are 100 per cent confident that the RTS Link project will be completed and operational by Jan 1, 2027,” he added.
Once finished, the civil structures will be handed over to RTS Operations, a joint venture formed in 2020 between Singapore rail operator SMRT and Malaysian public transport firm Prasarana, for rail systems to be installed.
Singapore’s Acting Transport Minister Chee Hong Tat said this next phase will entail the installation and testing of railway tracks as well as signalling and communications systems.
Remote video URL
Architectural works to fit out the respective terminus stations will be carried out at the same time, along with electrical and mechanical works.
This phase will require close coordination between both countries, Mr Chee added.
In their statement on Jan 11, the transport ministries highlighted the challenges that went into constructing the connecting span in the middle of the strait.
Weighing 340 tonnes, the span was built using temporary support structures consisting of steel beams and hydraulic jacks that had to be lined up precisely. The structures were erected at a height of more than 26m above sea level.
Prime Minister Lee Hsien Loong (centre right) and Malaysian Prime Minister Anwar Ibrahim (centre left) met at the strait in a ceremony to commemorate the milestone. ST PHOTO: KEVIN LIM
Passport-free immigration clearance being explored under Johor-S’pore Special Economic Zone
JB-S’pore RTS fares will be ‘competitive’, to be set nearer completion of project: Anthony Loke
The ministries said prolonged exposure to the elements and conducting installation works requiring millimetre precision under strong wind conditions presented an added challenge.
They added that these works had to be monitored closely to ensure they were being carried out safely and in a timely manner.
On Singapore’s end, the Land Transport Authority (LTA) said construction works for the Customs, Immigration and Quarantine (CIQ) building in Woodlands North, the 730m-long rail viaduct and connecting tunnels are progressing well.
The Johor Bahru-Singapore Rapid Transit System Link tunnels (left) and land viaducts (right) under construction on Dec 20, 2023. ST PHOTO: GAVIN FOO
These works started in 2021 after Singapore broke ground on the project in January that year.
LTA said all 12 pile caps, which form the foundation for the piers that support Singapore’s section of the RTS viaduct, have been completed, and construction of the viaduct piers is ongoing.
The RTS Link station in Woodlands North is being built at a maximum depth of 28m, and an underground Basement 3 linkway connecting the station to the CIQ building has been completed as well.
The construction of the Johor Bahru-Singapore Rapid Transit System Link Woodlands North Station on Dec 20, 2023. ST PHOTO: GAVIN FOO
A key feature of the cross-border rail link is that the CIQ facilities of both Singapore and Malaysia will be co-located at the Woodlands North and Bukit Chagar stations. This means passengers need to clear immigration only at their point of departure.
The CIQ facilities of both Singapore and Malaysia will be co-located at the Woodlands North and Bukit Chagar stations. ST PHOTO: GAVIN FOO
Malaysia’s MRT Corp said the pier columns for its section of the viaduct in the Strait of Johor are substantially completed.
On land, construction of the RTS Link train depot in Wadi Hana, Johor, is almost at the halfway mark, and piling works for the CIQ complex in Bukit Chagar are done.
Bukit Chagar station is about 40 per cent finished.
Remote video URL
The RTS Link ceremony on Jan 11 was part of an official visit by PM Lee to Johor – his first overseas visit in 2024.
Following the ceremony, PM Lee and Mr Anwar witnessed the signing of a memorandum of understanding on the Johor-Singapore Special Economic Zone.
The zone aims to improve the flow of goods and people between both sides of the Causeway, and enhance the ecosystem of the Iskandar development region and Singapore.
Embed Facebook
Made my first working visit of the year to Johor this morning! Joined Malaysian PM Anwar Ibrahim for the completion of...
Posted by Lee Hsien Loong on Wednesday, January 10, 2024
Remote video URL
Interactive: JB-Singapore RTS Link back on track
Visible progress of upcoming RTS Link draws S’porean, Malaysian buyers to JB properties
Unlock unlimited access to ST exclusive content, insights and analyses
ST One Digital - Annual
$9.90 $4.95 /month
Get offer
$59.40 for the first year and $118.80 per year thereafter.
ST One Digital - Monthly
29.90 $9.90 /month
Subscribe today
No lock-in contract
Unlock more knowledge, unlock more benefits
New feature: Stay up to date on important topics and follow your favourite writers with myST All subscriber-only content on ST app and straitstimes.com Easy access any time via ST app on one mobile device
Join ST's WhatsApp Channel and get the latest news and must-reads.
RTS/RAPID TRANSIT SYSTEM LINK RTS LINK MRT
Facebook Telegram More Whatsapp Linkedin Twitter FB Messenger Email Print Purchase Article Copy permalink https://str.sg/s3qZ
Read this subscriber-only article for free!
Just sign up for a free account and log in to continue reading.
JB-Singapore RTS Link: Construction passes 65% mark on both sides, connecting span completed
Sign up
Already have an account? Log in.
All done! This article is now fully available for you
JB-Singapore RTS Link: Construction passes 65% mark on both sides, connecting span completed
Read now
Please verify your e-mail to read this subscriber-only article in full
JB-Singapore RTS Link: Construction passes 65% mark on both sides, connecting span completed
Resend verification e-mail
The gift link for this subscriber-only article has expired.
Get unlimited access to all stories at $0.99/month for the first 3 months.
Subscribe now
You have reached your limit of subscriber-only articles this month.
Get unlimited access to all stories at $0.99/month for the first 3 months.
Subscribe now
Read and win!
Read 3 articles and stand to win rewards
Let's go! Terms & conditions apply
Frequently asked questions
Good job, you've read 3 articles today!
Spin the wheel now
Let's go! Terms & conditions apply
Frequently asked questions