用户名/邮箱
登录密码
验证码
看不清?换一张
您好,欢迎访问! [ 登录 | 注册 ]
您的位置:首页 - 最新资讯
Metro could take control of Silver Line’s second phase in November
2021-09-10 00:00:00.0     华盛顿邮报-华盛顿特区     原网页

       

       Metro officials said Thursday the transit agency could take ownership of the Silver Line extension project in November, paving the way for a possible opening of the long-delayed project during the first quarter of next year.

       Support our journalism. Subscribe today. ChevronRight

       Construction of the nearly 11-mile second phase of the Silver Line, which would extend rail service from the Wiehle-Reston East Metro station to Dulles International Airport and through to Ashburn, has been plagued by issues that include misaligned track and weak concrete panels, delaying its opening by nearly two years.

       Andrew Off, Metro’s vice president of the Rail Operations Control Center and Strategic Transformation, told Metro board members the transit agency has been told the project is scheduled for “substantial completion” in November, at which point Metro could take ownership, begin testing and prepare to start service. Construction of the extension is being overseen by the Metropolitan Washington Airports Authority.

       Advertisement

       Story continues below advertisement

       While Metro officials did not give board members an expected opening date, transit officials repeatedly have said they could need three months or more for testing before opening the line, which includes six stations.

       Silver Line setback likely to delay rail service to Dulles airport, Loudoun County

       “The airports authority still forecasts fourth quarter of this calendar year as declaring substantial completion,” said Off.

       He said MWAA started testing trains and the train control system on the line late last month, which he called a “major milestone.” MWAA officials didn’t immediately respond to a request for comment Thursday.

       “Once substantial completion is declared, we enter an undefined — in time — period called operational readiness testing,” said Off. “This is our opportunity to complete and witness and document all tests.”

       Story continues below advertisement

       While the project’s contractor has estimated the testing period would last about 60 days, Off said the transit agency can take the time it needs to prepare for opening.

       “We’re often hesitant to get too far out in front of a timeline for that event,” said Off.

       Once satisfied with testing, said Off, Metro would take about three months to ramp up staffing and assign roles to maintain and operate stations and the track.

       


标签:综合
关键词: completion     Silver     Metro officials     Dulles International Airport     transit     testing     project     rail service    
滚动新闻