用户名/邮箱
登录密码
验证码
看不清?换一张
您好,欢迎访问! [ 登录 | 注册 ]
您的位置:首页 - 最新资讯
443 infrastructure projects hit by cost overrun of Rs 4.92 trillion in Feb
2024-03-31 00:00:00.0     商业标准报-经济和政策     原网页

       

       As many as 443 infrastructure projects, each entailing an investment of Rs 150 crore or above, were hit by a cost overrun of more than Rs 4.92 trillion in February 2024, an official report stated.

       According to the Ministry of Statistics and Programme Implementation (MoSPI), which monitors infrastructure projects worth Rs 150 crore and above, out of 1,902 projects, 443 reported cost overruns and 764 projects were delayed.

       Click here to follow our WhatsApp channel

       "Total original cost of implementation of the 1,902 projects was Rs 27,08,030.44 crore, and their anticipated completion cost is likely to be Rs 32,00,507.55 crore, which reflects overall cost overruns of Rs 4,92,477.11 crore (18.19 per cent of original cost)," the ministry's latest report for February 2024 said.

       According to the report, the expenditure incurred on these projects till February 2024 is Rs 16,76,739 crore, which is 52.39 per cent of the anticipated cost of the projects.

       However, the number of delayed projects decreases to 568 if the delay is calculated on the basis of the latest schedule of completion, it added.

       Further, it said that for 389 projects, neither the year of commissioning nor the tentative gestation period has been reported.

       Out of the 764 delayed projects, 188 have overall delays in the range of 1-12 months, 185 have been delayed for 13-24 months, 275 projects for 25-60 months, and 116 projects have been delayed for more than 60 months.

       The average time overrun in these 764 delayed projects is 36.27 months.

       Reasons for time overrun, as reported by various project implementing agencies, include delay in land acquisition, obtaining forest and environment clearances, and lack of infrastructure support and linkages.

       Delays in tie-up for project financing, finalisation of detailed engineering, change in scope, tendering, ordering and equipment supply, and law and order problems are among other reasons.

       The report also cited state-wise lockdowns due to COVID-19 (imposed in 2020 and 2021) as a reason for the delay in the implementation of these projects.

       It has also been observed that project executing agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are under-reported, it added.

       Also Read

       411 infra projects show cost overruns of Rs 4.31 trillion in Oct: Report

       421 infra projects hit by cost overrun of Rs 4.40 trn in Nov, says MoSPI

       431 infra projects hit by cost overrun of Rs 4.80 trn in Jan, says Mospi

       As many as 431 infra projects show cost overrun of Rs 4.82 trillion in Dec

       JSW Infra makes strong debut; extends gain to zoom 32% over issue price

       Dividend receipts from CPSEs exceed revised estimates by 26% to Rs 63K cr

       Need to cut our expenditures, take Pak towards self-reliance: PM Shehbaz

       GDP set to grow at least 8% in Jan-March quarter: FM Nirmala Sitharaman

       IMF to increase Egypt's bailout loan to $8 billion to shore up its economy

       India's forex reserves rise by $140 mn to hit fresh peak of $642.63 bn

       (Only the headline and picture of this report may have been reworked by the Business Standard staff; the rest of the content is auto-generated from a syndicated feed.)

       


标签:经济
关键词: overrun     report     delayed     MoSPI     infra     crore     1,902 projects     February    
滚动新闻