Covid-19 delays work to rebuild collapsed viaduct in Changi, now due to open in Q2 2022
2021-09-19 00:00:00.0     海峡时报-新加坡     原网页

       

       SINGAPORE - A long-delayed road project in Changi will be further delayed, another in a list of infrastructural projects derailed by the pandemic.

       In response to queries from The Straits Times, the Land Transport Authority said the Tampines Expressway-Pan Island Expressway "Changi" viaduct project has been "affected by manpower and supply disruption due to Covid-19".

       "The project is now expected to be completed in the second half of next year, from first half of 2022," a spokesman added. "We are monitoring the progress of the project closely."

       Construction of the viaduct was initially undertaken by local builder OKP Holdings for $94.6 million in 2015. It was to be completed by the first quarter of 2020.

       But a collapse of a section in July 2017 - caused by a series of erroneous designs, poor oversight and cover-ups - delayed works. The collapse killed one worker and injured 10 others.

       Hwa Seng Builder eventually took over the project for $95.6 million. Work resumed in 2019, and the viaduct was scheduled to open in first half of 2022.

       But the pandemic threw a spanner in the works. Among other things, it crimped worker supply because of stricter border movements and quarantine requirements. Curtailed freight movements have also caused a shortage of materials, according to industry players.

       When completed, the viaduct is expected to ease congestion by letting motorists travelling from the TPE to the PIE and Upper Changi Road East bypass a stretch of the TPE between the Loyang and Upper Changi flyovers, as well as existing signalised junctions with Loyang Avenue and Upper Changi Road North.

       Motorists using that stretch of road have been waiting to use the viaduct for a number of years now.

       Changi resident Sarjeet Singh said: "I was looking forward to the opening as I have been seeing the progress."

       The 55-year-old lawyer added: "I guess I won't hold my breath any more in case I get disappointed again."

       Another Changi resident, 62-year-old businessman Raymond Ang, said: "I can't fault the authorities on this. It was no fault of theirs."

       Still, Mr Ang said the construction has "caused great inconvenience" to residents in the vicinity. "Traffic will always be slowing down over that stretch," he said. "It's a huge bugbear. It's frustrating, but what can we do about it?"

       More on this topic

       Related Story

       New roads, viaduct to serve Changi region including future T5

       Related Story

       Construction firm fined maximum $1 million over 2017 PIE viaduct collapse; 2 employees jailed

       Several other land transport projects are also delayed. The Thomson-East Coast MRT line was originally due to fully open in 2024, but it will now be completed in 2025.

       The sixth stage of the Circle MRT line, which joins Harbourfront and Marina Bay to make a complete circle, was initially due to open in 2025. It will now be completed in 2026.

       The Jurong Region Line, a medium-load rail line which was first mooted in 2001 and given the go-ahead in 2013, was originally scheduled for completion n 2025. It will now fully open in 2029.

       The Cross Island MRT line, which spans Changi to Jurong and cuts through the nature reserve, was to be completed in 2030. It will now be up by "the 2030s".

       Elsewhere, construction of the North-South Corridor, an expressway with bus and cycling lanes, was to have started in 2015 and be done by around 2020.

       The start date was postponed because of a redesign to accommodate buses and bicycles, with completion eventually targeted for 2026. This has been delayed to 2027 due to Covid-19.

       More on this topic

       Related Story

       Commuters on first trains at new TEL2 stations reminisce about inaugural 1980s MRT rides

       Related Story

       Multiple traffic diversions needed from end-2021 for construction of Loyang MRT station

       Join ST's Telegram channel here and get the latest breaking news delivered to you.

       Topics:

       More Whatsapp Linkedin FB Messenger Telegram Reddit WeChat Pinterest Print Purchase Article Copy permalink https://str.sg/3SaN

       


标签:综合
关键词: viaduct project     Loyang     Expressway     construction     delayed     completed     Jurong     Changi    
滚动新闻